Product Team · Delivery Plan

Eight weeks,
seven workstreams.

F8 lands in week 1. The Financial Intelligence Hub, DeskLoad and CRT build through the first three weeks; week 4 is a UI-enhancement push across the systems, then UI development, testing and handovers follow. Productivity UI stays at concept stage this window. Snippy V1 runs as ongoing support throughout.

Window
13 Jul → 06 Sep 2026
Workstream
W1
13–19 Jul
W2
20–26 Jul
W3
27 Jul–2 Aug
W4
3–9 Aug
W5
10–16 Aug
W6
17–23 Aug
W7
24–30 Aug
W8
31 Aug–6 Sep
Milestones
F8 Message Integration
BestPractice messaging
Integrate
Financial Intelligence Hub
Debt collection · was Finance Report
Func. dev
Test
Handover
UI enh.
UI dev
Handover
DeskLoad
Reception capacity
Functional dev
UI enh.
UI dev
Test
Handover
Productivity UI Prototype
Concept · Kenny + Aman
Overview concept
UI enh.
→ dev · testing · handover after the window
Refine concept (K+A)
CRT
Call review tool
Functional dev
UI enh.
UI dev
Test
Handover
Tasky
Internal · no BP
Prototype review
UI enh.
Functional dev
Test
Handover
Snippy V1
Support · no prototype
Ongoing support across the 8 weeks toward V1
F8
Financial Hub
DeskLoad
Productivity UI
CRT
Tasky
Snippy
Review / deferred
Milestone

Week 4 is a UI-enhancement push across DeskLoad, CRT and Tasky. Every tool ends in internal testing and a handover for small-group testing; feedback from those handovers is worked on after the eight weeks. Productivity UI stops at concept + UI this window, its build, testing and handover come later.

Milestones
END OF WEEK 1
19 Jul
  • F8 message integration delivered
END OF WEEK 4
9 Aug
  • Financial Intelligence Hub handed to finance & management (functional)
  • UI enhancement underway across DeskLoad, CRT & Tasky
END OF WEEK 7
30 Aug
  • Financial Hub (UI version) handed over
  • DeskLoad handed over
  • CRT handed over for testing
END OF WEEK 8
6 Sep
  • Tasky handed over for small-group testing
  • Snippy V1
  • Productivity UI continues after the window
What each workstream is
How it fits together

The shared lifecycle

Most systems follow the same path, with week 4 as the common UI-enhancement point.
Functional dev
weeks 1–3
UI enhancement
week 4
UI development
week 5
Internal testing
week 6
Handover
week 7

DeskLoad and CRT run this exactly. The Financial Intelligence Hub runs slightly ahead, it hands a functional version to finance & management at week 4, then does its own UI pass (weeks 5–7). Tasky is offset: UI enhancement at week 4, then build from week 5, handover at week 8. Productivity stops after concept + UI enhancement; its development, testing and handover fall after the window.

Handover timing

When each workstream reaches internal users.
F8
week 1
·
Financial Hub
week 4 (functional) · week 7 (UI)
·
DeskLoad · CRT
week 7
·
Tasky
week 8

Feedback from every handover is collected during the window and worked on afterwards.

Product Team · 8-week delivery plan · 13 Jul – 6 Sep 2026
Week 1: F8. Weeks 1–3: build (Financial Hub, DeskLoad, CRT) + Productivity concept. Week 4: UI enhancement + Financial Hub handover. Weeks 5–8: UI development, testing, handovers. Snippy V1 supported throughout.